Grant Chart

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Cost

Library Management System

160 days

Mon 6/10/19

Fri 1/17/20

   

AED 3, 00,000

   Planning

10 days

Mon 6/10/19

Fri 6/21/19

 

Systems analyst

2, 000

      Appointment of project manager

3 days

Mon 6/10/19

Wed 6/12/19

   

1, 000

      First meeting

2 days

Thu 6/13/19

Fri 6/14/19

   

5, 00

      Deliberation and brainstorming

5 days

Fri 6/14/19

Thu 6/20/19

 

 

5, 00

   Proposal Development

10 days

Fri 6/21/19

Thu 7/4/19

 

 

4, 000

      Project requirements

1 day

Fri 6/21/19

Fri 6/21/19

 

Project Manager

5, 00

      Project schedule

4 days

Mon 6/24/19

Thu 6/27/19

7

 

5, 00

      Project budget

3 days

Thu 6/27/19

Mon 7/1/19

 

 

5, 00

      Project objectives

1 day

Fri 6/28/19

Fri 6/28/19

 

 

5, 00

      Project Proposal

1 day

Sat 6/29/19

Sat 6/29/19

 

 

2, 000

   Team Selection

9 days

Sat 6/29/19

Wed 7/10/19

 

Project Manager

4, 000

      Vacancy Advertisement

3 days

Sat 6/29/19

Tue 7/2/19

 

 

5, 00

      Interview and selection

4 days

Tue 7/2/19

Fri 7/5/19

 

 

1, 500

      Appointment and briefing

3 days

Fri 7/5/19

Tue 7/9/19

 

 

2, 000

   Material Acquisition

10 days

Wed 7/10/19

Tue 7/23/19

 

Project Manager

8, 000

      Acquisition of barcode readers

6 days

Wed 7/10/19

Wed 7/17/19

 

 

3, 000

      Acquisition of computers

4 days

Wed 7/17/19

Mon 7/22/19

 

 

5, 000

   System analysis

20 days

Tue 7/23/19

Mon 8/19/19

 

Systems developer

1, 000

      Combine system analysis information

20 days

Fri 7/19/19

Thu 8/15/19

 

 

1, 000

   System Design

10 days

Mon 7/15/19

Fri 7/26/19

 

Systems developer

1, 000

      Design software component

5 days

Mon 7/15/19

Fri 7/19/19

 

 

5, 00

      Design hardware component

5 days

Fri 7/19/19

Thu 7/25/19

 

 

5, 00

   Software Development

25 days

Fri 7/26/19

Thu 8/29/19

 

Systems developer

6, 000

      Inventory component

15 days

Fri 7/26/19

Thu 8/15/19

 

 

2, 000

      Catalogue component

5 days

Thu 8/15/19

Wed 8/21/19

 

 

2, 000

      Borrowing and returning component

5 days

Wed 8/21/19

Tue 8/27/19

 

 

2, 000

   Hardware Integration

10 days

Wed 8/28/19

Tue 9/10/19

 

Project Manager

1, 000

      Barcode integration

3 days

Wed 8/28/19

Fri 8/30/19

 

 

5, 00

      Computer terminal integration

7 days

Sat 8/31/19

Mon 9/9/19

 

 

5, 00

   Integration Testing

10 days

Mon 9/9/19

Fri 9/20/19

 

Systems tester

5, 00

      hardware Integration testing

10 days

Mon 9/9/19

Fri 9/20/19

 

 

5, 00

   System Testing

10 days

Fri 9/20/19

Thu 10/3/19

 

Systems tester

5, 00

      Unit testing

3 days

Fri 9/20/19

Tue 9/24/19

 

 

3, 00

      Acceptance testing

7 days

Tue 9/24/19

Wed 10/2/19

 

 

3, 00

   System Deployment

10 days

Fri 10/4/19

Thu 10/17/19

 

 

1, 500

      System installation

3 days

Fri 10/4/19

Tue 10/8/19

 

 

3, 00

      End-user training

3 days

Tue 10/8/19

Thu 10/10/19

 

 

1, 100

      System monitoring and troubleshooting

4 days

Thu 10/10/19

Tue 10/15/19

 

 

1, 00

   Documentation

5 days

Thu 10/17/19

Wed 10/23/19

 

 

5, 00

NO PLAGIARISM POLICY - ORDER NEW LIBRARY MANAGEMENT SYSTEM ASSIGNMENT AND GET WELL WRITTEN SOLUTIONS DOCUMENTS WITH FREE TURNTIN REPORT!

MS Project:

LMS.jpg

Here we have shown the work schedule of Library Management System that how many days have been given to Planning of project and all other information is gathered in different forms. After planning we will gather all information and fix the appointment of project manager and then first meeting is held on 6/13/19 which will take 2 days' time and cost 2, 000.Then the proposal development process will take place with different process like Project requirements, Project schedule, Project budget and many more which start on 6/21/19 and takes 10 days' time. The Team selection is vacancy advertisement and interview and selection of the project on the system whose budget is 4, 000 and their interview briefing will take place for 3 days continuously. Then Material acquisition and system analysis will take 10 and 20 days respectively. Then they will plain for system design which will take 10 days and start on 7/15/19.Befor developing the software we need to design the software components and all other aspects. The system testing process will start on 9/20/19 and all the aspect of software developing process will be shown in the system development process. In these method all are included in the system which will include it in the process and check all the methods as per the method.

And then software development process will start which will take 25 days and budget of 6000 and after development hardware integration process will take. Hardware integration will also been include in the development process so that we can check the hardware requirement of the system. And then different testing process will take place and at last the documentation will start which will take 5 days only and the system development will finish on 10/23/19 with total cost invested in this project is 3, 00,000.

Network Diagram:

Network Diagram.jpg

In this diagram shown we have shown different steps of development which has been shown here .In the network diagram all the process in the software development has been included and its starting and end date has been mentioned. The system analysis shows all the process and starts on 23/07/19 and finishes on 1/8/19 on the month, so it will take 20 days to analyses the system and start the next process. All these` process are the part of software development and check the date and all the process of software development will be shown with the cost invested in it. All these process shown the competition percentage of the system and the system analysis process start on 10th June '2019.In the network diagram the connectivity of all the methods are shown as per the expectation of the process and in each method detailed of the process.

GET READYMADE LIBRARY MANAGEMENT SYSTEM ASSIGNMENT SOLUTIONS - 100% PLAGIARISM FREE WORK DOCUMENT AT NOMINAL CHARGES!

Tag This :- EM201962AZZ610PM, Library Management System Assignment Help

get assignment Quote

Assignment Samples

    Case Manager Assignment Help

    case manager assignment help - the paper is related to the strategic implementation of the case study in the given scenario.

    Change Management Assignment Help

    change management assignment help - The concept of change management has been analysed in the task with regard to the changes in the organisational structure.

Get Academic Excellence with Best Skilled Tutor! Order Assignment Now! Submit Assignment