Looking For ENGG 0004 Project Management Assignment Help? Approach Us And Get Help From Skilled Tutors!!

Home   Course  
Previous << || >> Next

DO WANT TO HIRE TUTOR FOR ORIGINAL XXXX ASSIGNMENT SOLUTION? AVAIL QUALITY ENGG 0004 PROJECT MANAGEMENT ASSIGNMENT WRITING SERVICE AT BEST RATES!

ENGG 0004 Project Management Assignment - Middle East College, Oman

INTRODUCTION: The purpose of the proposal is to create a plan to be followed in doing course work project in Project Management module.

LEARNING OUTCOMES - 1. Apply basic principles of management to the use of materials, plant and labour on construction projects.

2. Identify the issues involved in securing productivity gains In construction.

3. Produce programmes for low complexity projects using appropriate manual techniques.

4. Use project planning software to generate master programmes for simple construction or design projects.

TASK: In the project, students will have hands-on experience in developing an integrated framework for the planning, scheduling, resource management, project costs and project control.

Answer - Project Management

1. Introduction

Construction of warehouses and distribution needs expertise, great project management and an awareness of how the finished project will have to work.The strategy adopted for this debate will concentrate first on the policy issues facing big and complicated project management. It will then address the different features of project management, how this activity can be facilitated by an incorporated information warehouse and the assessment criteria to determine the comparative achievement of a project.Once we have a clear knowledge of the Company Task, we will examine the available data assets from which to enable efficient decision-making. Finally, we're going to concentrate on the Project Management Warehouse itself; what it is, how to most efficiently construct and implement it.

The warehouse contains seven areas: receiving area, shipping, packing supplies, assembly area of orders, storage, offices and mixed area. Mainly we have the four resources crane, excavator, labor and materials used in construction in warehouse.Materials required for the warehouse construction include the reinforced cement concrete, bricks for wall construction, sheets for walls and roofing (sheets must be waterproof), for floor construction we will used the RCC (Reinforced Cement Concrete) or the VDC (Vacuum Dewatered Concrete), MS steel, MS steel girders, pedestals, sand and stones for making concrete.

We will build the halls with the concrete. It is possible to implement concrete halls either with joist-based structural frameworks or using a panel-based structure. Over the past few years, the material has drawn more and more followers, partly due to the option of incorporating concrete into recycling procedures.Corrugated fiber cement sheeting can be considered one of the classic roofing choices for halls as well as other building types. The robust sheets are fast to attach and in a multitude of colors and forms available.

GETTING STUCK WITH SIMILAR ENGG 0004 PROJECT MANAGEMENT ASSIGNMENT? ENROL WITH EXPERTSMINDS'S ENGG 0004 PROJECT MANAGEMENT ASSIGNMENT HELP SERVICES AND GET DISTRESSED WITH YOUR ASSIGNMENT WORRIES!

2. Description

A main emphasis on either price control or timetable control is prevalent in the development of a building plan.Some projects are split mainly into classifications of expenses with related expenses. Building planning is cost or expense oriented in these instances. Within the investment classifications, a difference is created between expenses directly incurred in carrying out an operation and subsequently for carrying out the design.Work scheduling is critical over time and is highlighted in the construction process. In this situation, the planner ensures that the correct precedence between operations is retained and that the necessary resources are effectively scheduled.Traditional planning processes reinforce the management of work precedents resulting in the scheduling of critical paths or the effective use of funds over time resulting in the scheduling of session processes.Lastly, most complicated projects involve consideration of both price and schedule over time, so that both dimensions need to be considered in planning, tracking and record keeping. In these instances, it is a significant problem to integrate timetable and budget data.

Project Management Assignment.png

Defining suitable job duties can be a painstaking and time consuming method, but it is the data needed to apply formal planning processes. Because infrastructure projects can involve hundreds of individual job duties, this stage of concept can also be costly and time-consuming.Many duties can be repeated in separate areas of the building or previous building plans for fresh projects can be used as overall models.The tasks engaged in constructing floor development can be recurring with only slight variations for each of the building layers. Also, for most assignments, there are normal definitions. As a consequence, not every aspect of the venture must be approached completely from scratch by the individual planner defining job functions.While repeating activities at distinct places or reproducing activities from previous projects decreases the job involved, the method of defining operations has very few computer aids.Many computer programs are accessible for the planning process itself. But dependence on the building planner's ability, judgment, and understanding is likely to continue for the significant job of defining operations.

Most crucial factor of constructing a warehouse is proper designing. As a project manager we need to take into account various methods and processes while designing the construction part. First we need to understand the goods that are going to be stored and accordingly we will design the height of the roof. The taller the roof, it is better for the storage of goods. In a general case the height of the pallet racking must be 40 feet or more.By cubing the building, this sort of scheme maximizes the warehouse's square footage. It also reduces travel time when carrying item from a location to another location.We will minimize all travel distances. After that we will calculate the total number of wood sheet required for the construction of the warehouse and other section and we will gathered all required sheets with an extra 5% margin. After accumulating all required material we will start the tough work as per the planned design. We also have to level the soil before construction. In order to generate a level zone for the construction soil a road surface for trucks shipment, we might need extra soil for leveling the ground or the extra soil would need to remove. Parking for employees and other factors also need to be considered at this stage. Besides the concrete base, it will also be necessary to lay concrete truck pads at each gate. To do the cost cutting we can also use the bitumen for the parking area construction rather than the RCC.

ORDER NEW COPY OF ENGG 0004 PROJECT MANAGEMENT ASSIGNMENT AND SECURE HIGHER MARKS!

The building structure will be constructed on top of the foundation, composed usually of a sequence of heavy metal steel beams and girders. Asarcophagus will be constructed, which is of light weighted material, over these massive girders and we include the silhouette intended for doors or windows in the construction.We will apply sheets of metal on this frame. Sheets of metals are attached from the body. After that we fix them with a dense radiant barrier on the inside. Upon completion of the exterior shell, the windows and doors will be mounted and all decorative jobs will be finished.The interior work starts with the exterior completed. The sprinkler system will be the first thing mounted, preceded by any central air systems. It is possible to finish any headquarters and toilets will become functional. The warehouse filling is prepared to be installed with these components in location and the transportation lanes and routes are obviously labeled.This is when any special characteristics like a battery docking station or repair fields are mounted. The warehouse is prepared to house merchandise once these are complete.

Project Schedule:

Outline Number

Task Name

Duration

Start

Finish

Predecessors

1

Design

10 days

Mon 1/9/19

Fri 10/9/19

1

2

   Programming feasibility

6 days

Mon 11/9/19

Mon 17/9/19

3

3

Schematic design

3 days

Mon 18/9/19

Wed 21/9/19

2

4

Design development

3 days

Thu 22/9/19

Mon 25/9/19

3

5

Contract documents

4 days

Tue 26/9/19

Fri 30/9/19

4

6

      Pre-construction

2 days

Tue 1/10/19

Wed 2/10/19

4

7

Assign a project team

2 days

Thu 3/10/19

Fri 4/10/19

6

8

Site investigation

7 days

Mon 5/10/19

Thu 12/10/19

7

9

Procurement

6 days

Mon 13/10/19

Mon 19/10/19

7

10

Labor

4 days

Tue 20/10/19

Fri 23/10/19

9

11

Materials

4 days

Mon 24/10/19

Thu 27/10/19

10

12

Equipment

5 days

Fri 28/10/19

Tue 2/11/19

11

13

Pre-construction meeting

5 days

Fri 3/11/19

Fri 7/11/19

11

14

Move onto a construction team

3 days

Mon 8/11/19

Tue 10/11/19

13

NEVER BE CAUGHT IN PLAGIARISM, AVAIL ENGG 0004 PROJECT MANAGEMENT ASSIGNMENT HELP SERVICE OF EXPERTSMINDS.COM AND SAVE HIGHER MARKS!

3. Conclusion

Begin by looking at your present warehouse feature to create a strategic plan for your warehouse. This will require examining your existing equipment.Create a precise outline of the construction and floor plan of your warehouse. Make sure that it is to scale so that precision can be maintained. Confirm the sketch manually by looking at the ground of the warehouse.Record all your warehouse materials. In each section of your warehouse, write down processes and personnel obligations. Look at the operations you have in location and what's occurring on the ground of the warehouse.Many variables affect the cost of warehouse construction - market circumstances, property costs, never to discount the sort of warehouse. And because the demands of each project are distinct, there is no cookie-cutter way to get a precise assessment of the cost of building warehouse. It is the responsibility of your construction partner to find cost-saving design alternatives that will reduce expenses and create value.The manner and equipment used to build a plant are an extra determining factor in the price of the warehouse building. Most warehouses are either constructed using tilt-up cement or pre-engineered maintenance of metal. In some situations, each has its advantages and disadvantages.Pre-engineered metal structures on smaller scales are less costly. Scale economies apply to big warehouses and distribution centers: As square footage rises, the concrete tilt-up technique becomes more cost-effective. Tilt-up warehouses also include a greater life cycle.Tough costs include cost, such as labor and material, easily predictable. While these may seem simple to schedule around, the cost of products may vary extensively depending on the circumstances of the ecosystem and the industry.

EXPERTSMINDS.COM GIVES ACCOUNTABILITY OF YOUR TIME AND MONEY - AVAIL TOP RESULTS ORIGINATED ENGG 0004 PROJECT MANAGEMENT ASSIGNMENT HELP SERVICES AT BEST RATES!

Get our Middle East College Assignment Help services for below mentioned courses like:-

  • ENGG 0001 Engineering Science Assignment Help
  • ENGG 0002 Design and Visualisation Assignment Help
  • ENGG 0003 Project Assignment Help
  • MASC 10005 Statistics Assignment Help
  • BUSS 10003 Fundamentals of Business and Organization Assignment Help
  • BUSS 10004 Marketing Principles and Practice Assignment Help
  • BUSS 23001 Principles of Financial Investment Assignment Help
  • LANG 10003 Academic English for International Business Assignment Help
Tag This :- WPS654370208PRO ENGG 0004 Project Management Assignment Help

get assignment Quote

Assignment Samples

Get Academic Excellence with Best Skilled Tutor! Order Assignment Now! Submit Assignment